Home
Site Map
About Substations
Formats
Auxiliary Relays
Equipments Formats
Protection Formats
>
Energization Tests
Functional Test Format
Manuals
Software
Support
Testing & Commissioning
Test Procedures
Relays Calculations
Relays Configuration
Tutorials
References
Label Design
Blog
About Me
Energy Meter Testing
Testing Procedures
Meter Measurement.
Calibrate Energy Meter (Accuracy Test).
Calibrate Energy Meter (Impulse Test).
Download:
Energy Meter Test Format.
Equipment Required
Injection Kit: Freja 300.
Calibration Meter: Calport100.
Connection Cables (Banana Type).
Test switch (Test Plug).
FREJA 300
Calport 100
Test Swtich
Connection Cables
Software Installation
Install driver of
Opto Cable probe
(Communication between Energy Meter & PC).
Install
Metercat
Software.
Check at which COM port no. Optical Probe is Connected: From My Computer Properties - Hardware - Device Manager - Ports (COM & LPT).
Start Using Metercat:
Choose
Single User
.
Default Username:
Administrator
.
Default Password:
Administrator
.
Identify Opto Probe: from
Tools
choose
Machine Setting
, then choose
Optical Probe
-
edit
- choose COM no.
From
Connection
choose
Optical Probe
.
From
File
menu -
New Program
.
Choose Time of Use, then install your program according to Energy Meter Type - Save Program.
From
Properties:
activate
Relay Option
.
From
Constants:
change VT Ratio & CT Ratio.
From
Display:
activate all display labels for
Normal Mode
,
Alternative Mode
&
Test Mode
.
From
File
- Save configuration.
Upload the configuration file to energy meter, from
Function
- choose
Program
then
Go
, choose configuration file then OK.
To reset all Meter readings & demand: from
Function
choose
Reset
Demand
then
Go
.
To reset cumulative demand:
from
Function
choose
Register Edit
then
Go
- make all readings
zero
then OK.
Meter Calibration Test
Connection will be same as the shown figure.
Standard Meter is used to show actual values of Current & Voltage injected by FREJA.
Adjust CT & VT Ratio on standard meter.
Standard meter measurement is in primary values.
Inject rated current & voltage to check Energy meter measurements.
Start Injection & Start Standard Meter for accuracy test.
Start injection with 25% of rated current with phase shift 30 degrees.
Standard meter will calculate actual injected Energy.
After certain time (15 minutes), stop injection & standard meter in the same time.
Read the cumulative demand:
from
Function
choose
Register Edit
then
Go.
Calculate the error between the energy meter & the standard meter.
Repeat previous test with different phase shift & calculate meter error in every case.
VT Connection
CT Connection
Home
Site Map
About Substations
Formats
Auxiliary Relays
Equipments Formats
Protection Formats
>
Energization Tests
Functional Test Format
Manuals
Software
Support
Testing & Commissioning
Test Procedures
Relays Calculations
Relays Configuration
Tutorials
References
Label Design
Blog
About Me